I got a job

Algebra Level 3

Prakash, Ramesh and Suresh started a job. After 2 days Prakash left. After another 2 days, Ramesh left. In another 2 days, Suresh completed the remaining part of the job. If Prakash can complete the same work in more than 6 days and Ramesh can complete it in more than 12 days, who got the highest share of the wages ?

×