A construction company will be penalised each day for delay in construction of a bridge. the penalty will be Rs.4000 for the first day and will increase by Rs.1000 for each following day. Based on its budget, the company can afford to pay a max. of Rs. 165000 towards penalty. find the max. no. of days by which the completion of work can be delayed.

×