UKMT Senior Challenge-VIII

Algebra Level 3

Twenty-five workmen have completed a fifth of a project in eight days. Their foreman then decides that the project must be completed in the next 20 days. What is the smallest number of additional workmen required to complete the project on time?

This problem is not original.This problem is part of this set.

×